A Key Power Supplier to AI Data Centres Has Record Orders. Its Stock Is Down 44%
Caterpillar, a leading supplier of gas generators to data centers, has lost $214 billion in market value since June 30, even as its order backlog climbed to a record $78 billion.
The world's largest construction equipment maker closed at $600.20 on November 13, nearly 44% below its peak. For shareholders, the question is whether the market sees a slowdown that orders do not yet reflect.
Strong Demand Disappoints
Caterpillar's third-quarter results showed strong demand. Sales and revenues rose 17% to $20.7 billion. Power generation sales jumped 75% year over year on data center demand, according to the Financial Times.
Even so, the stock fell 9.3% on October 29, the day of the report. Investors had expected a raised forecast, so the company's moderate fourth-quarter sales outlook disappointed them.
Election Impact
The midterm elections added fresh pressure. Voters backed data center limits in 40 of 41 local ballot measures, Ballotpedia reported. AI infrastructure stocks slid afterward, extending the wider AI trade selloff.
backlogs are trailing indicators. He said buyers were double and triple ordering to protect their place in the queue.
Historical Precedent
An FT analysis puts losses across global manufacturing, utility, and mining companies since June at $4.2 trillion. Telecom history shows how quickly backlogs can reverse. In 2001, major customers of Corning's photonics unit canceled orders, leading to a $5.5 billion net loss and 12,000 job cuts.
However, not everyone expects a repeat. Dell'Oro Group analyst Alex Cordovil told the FT that record backlogs lock in supplier revenue growth until 2027. Goldman Sachs CEO David Solomon has also defended the US data center buildout, warning that blocking it would push AI capacity overseas.